Progress Time Line
Chronological progress for September, 2007.
September 28, 2007, The three parking spaces along Meridian Road have been poured and the asphalt set. |
|
September 25, 2007, The sidewalk along Meridian Road from Main Street to the Bike Path has been poured. |
|
September 19, 2007, The curb for the parking spaces has been completed. The forms were set for the sidewalk and curbs along Meridian Road. And the new curb along Main Street has been completed. |
|
September 12, 2007, The aggregate base was spread out after dirt for the three parking spaces was excavated. A storm drain was installed and the trench was dug for water drainage. |
|
September 7, 2007, The monument site has been graded with the dirt that was delivered earlier this week. |
|
September 4, 2007, Backfill dirt has been delivered to the site for grading. |