Progress Time Line

Chronological progress for September, 2007.

September 28, 2007,
The three parking spaces along Meridian Road have been poured and the asphalt set.
Long Site shot along Meridian Road to show parking spaces
Site shot of parking spaces along Meridian Road
September 25, 2007,
The sidewalk along Meridian Road from Main Street to the Bike Path has been poured.
Site shot along Meridian Road to show sidewalk to Main Street
Site shot of intersection of sidewalk and bike path
Close up of Meridian Road sidewalk joining bike path
September 19, 2007,
The curb for the parking spaces has been completed.
The forms were set for the sidewalk and curbs along Meridian Road.
And the new curb along Main Street has been completed.
Site shot along Meridian Road to show parking spaces curbs
Close up of Meridian Road parking spaces curb and sidewalk
New curb along Main Street
September 12, 2007,
The aggregate base was spread out after dirt for the three parking spaces was excavated.

A storm drain was installed and the trench was dug for water drainage.
Gravel for parking spaces spread out
Gravel for Parking spaces site shot
Water drainage trench
Water drainage pipe and trench
September 7, 2007,
The monument site has been graded with the dirt that was delivered earlier this week.
Graded Site Main Street Graded Site with Front End Loader Right
September 4, 2007,
Backfill dirt has been delivered to the site for grading.
Backfill dirt for grading Removal of Power Poles at Intersection

 

GCV.org | ©2007-2012 Glen Carbon Veterans Monument Committee |